Terminal 5 Site Enabling Team

Site Search:
Terminal 5 Site Enabling Team

Statistics

Client:
BAA

Sector:
Aviation

Business:
MLogic

Service Carried Out:
Logistics Management

Value:
£40m

Project Dates:
Completed March 2007

Office:
London

Information

MLogic provided management staffing for the site enabling team, engage sub suppliers where necessary to deliver the management and integration of the logistics requirements at the Terminal 5 Concourse A (T5A) at Heathrow Airport.

Project challenges:

  • Material distribution to a 450m * 150m building over twelve floors.
  • Provide on site welfare and temporary services for 3,000 operatives.
  • Provide transport system within the building footprint for labour and material delivery.
  • Supply and manage 24no. hoists.
  • Support the principal contractor in discharging his duties under CDM regulations.

What MLogic brought to the project?
By allying our building experience with logistics skills, MLogic were able to provide an integrated logistics service to T5A that facilitates the construction of this major landmark project. This has included developing models to forecast material deliveries to the project, which enabled us to identify and implement the best logistics solution for the project.

Key Features of Works:

  • Independently supported hoist 35m high to the roof.
  • Provision of temporary services designed to integrate with permanent system.
  • Production and implementation of a site wide web based delivery management system.
  • Bar code material delivery recognition.
  • Best value procurement of delivery plant fleet.
  • Use of on site signage production capability with re use of old site materials for supports.
  • On site electronic signage for operative information.
  • Marshalling zones for material storage and waste removal.